Work Profile Report [36W459]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शासन की ई-फाईल संख्या 48456 एवं कम्प्यूटर जनित संख्या 185624/2024 दिनांक 30.01.2024
TS Amount (lakhs) : 151.7 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
151.70
Resanction Cost :
151.70
Tentative Cost :
151.70
Exp. Upto Last Fy :
4.99
For CFY 2024-2025
Remaining :
146.71
Demand :
146.71
Allotment :
127.42
Exp in CFY :
98.68
Total Up to Date Exp :
103.68
Construction Started
Sanction on : 9 months 3 weeks ago
30 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
45 %
Up to Date :
76 %
Tentative Completion date on : 3 months 1 week from now
04 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी॰सी॰ द्वारा डामरीकरण कार्य पूर्ण। दीवार निर्माण कार्य प्रगति में। -- as on 25-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: