Work Profile Report [38W24]

जनपद चमोली में गौचर-सिदोली मोटर मार्ग का विस्तार कि0मी0 24.500 से 27.500
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 312/।।।(2) /09-06 (मु0मं0घो0)/ 08 दि0 2.3.09

TS Amount (lakhs) : 110.25 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

110.25

Resanction Cost :

110.25

Tentative Cost :

110.25

Exp. Upto Last Fy :

61.74

For CFY 2024-2025

Remaining :

48.51

Demand :

2.47

Allotment :

10.24

Exp in CFY :

10.24

Total Up to Date Exp :

71.98

Construction Started

Sanction on : 15 years 8 months ago

02 Mar 2009

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
1.35
0.000
1.35
2.300
0.000

Remark

view all

वन भूमि की सै0स्वी0 भारत सरकार े प. 8बी0/यू.सी.पी./06/216/ 2017/एफ.सी./1670 दि0 12.11.2018 द्वारा प्राप्त। एन.पी.वी. रु. 21.27 लाख के भुगतान। दि0 28.12.2021 को वृक्षों के पातन के उपरांत पहाड़ कटान कार्य प्रगति में। वन भूमि पेकेज संख्या:- एफ.पी./यू.के./ रोड़/12951/2015 -- as on 31-Jan-2022

Rating : 84

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand