Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 10 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 15 | 15 | 15 | 0 |
38W429 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं.ः- 1843/।।।(2)/16-06(एम0एल0ए0)/ 2015 दि. 02.06.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
119.05
Resanction Cost :
119.05
Tentative Cost :
119.05
Exp. Upto Last Fy : 3.45
For CFY 2024-2025
Remaining : 115.60
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 3.45
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
8 years 1 month ago
02 Jun 2016
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 09: GOI
Bottelneck: Long Term Forest Approval
fववाद समाप्त कर सर्वे कार्य पूर्ण। संरेखण प्रस्ताव 08/2018 में स्वीकृत। वन भूfम प्रस्ताव fद0 05.03.2021 को आनलाइन। दि0 20.01.2023 द्वारा प्रस्ताव आपत्तियों में प्राप्त। वर्तमान में प्रस्ताव भारत सरकार को दिनांक 18/05/2023 द्वारा प्रेषित। -- as on 31-May-2023
Physical Peramenters