Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.43 | 4.43 | 4.43 | 0 |
38W532 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Bichona Shamshan Ghat Gadhera Pedestrain Bridge
Administrative Approval Detail : शा0सं0ः-642/।।।(2)/19-6(एम.एल.ए.)/2017 टी0सी0-।। दिनांक 12.02.2020
TS Amount (lakhs) : 312.93 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
312.93
Resanction Cost :
312.93
Tentative Cost :
312.93
Exp. Upto Last Fy : 312.90
For CFY 2024-2025
Remaining : 0.03
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 312.90
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 5 months ago
12 Feb 2020
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रारम्भ। रु0 16.15 लाख का आवंटन एवं व्यय राज्य योजना से किया गया है। दि0 26.03.2021 द्वारा कार्य नाबार्ड 26 में अनुमोदित। चैड़ीकरण का कार्य 80 प्रतिशत् पूर्ण। 4.43कि0मी0 में सोलिंग, इन्टर कोट , टोप कोट एवं पी0सी0 का कार्य पूर्ण। -- as on 19-Apr-2023
Physical Peramenters