Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
39W698 :
Administrative Approval Detail : शासनादेश संख्या 1326/।।।(2)/19-08 (एमएलए)/2017टीसी ।।। दिनांक 10.03.2019
TS Amount (lakhs) : 271.33 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
271.33
Resanction Cost :
271.33
Tentative Cost :
271.33
Exp. Upto Last Fy : 270.98
For CFY 2024-2025
Remaining : 0.35
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 270.98
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
10 Mar 2019
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूूर्ण। -- as on 30-Mar-2023
Physical Peramenters