Work Profile Report [3W10]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 793/111(2)/09-14(मु.मं.घो.)/09 दि. 12.03.09
TS Amount (lakhs) : 840.52 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
472.50
Resanction Cost :
472.50
Tentative Cost :
443.08
Saving
29.42
Exp. Upto Last Fy :
393.08
For CFY 2025-2026
Remaining :
79.42
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
393.08
Work completed
Sanction on : 16 years 9 months ago
12 Mar 2009
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
नापभूमि प्रतिकर प्रस्ताव गठन की कार्यवाही गतिमान। -- as on 02-Jan-2026
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Khalduwa over Mashangari River Balley Bridge