Work Profile Report [3W4]

जनपद अल्मोड़ा में घुघुती कैलानी से मसमौली तक मोटर मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Nabard
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 2454/111-2/05-07(प्रा0आ0)/05 टी.सी.-1 दि. 21.10.05

TS Amount (lakhs) : 505.01 Lacs

Budget Financial Head : NABARD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

139.00

Resanction Cost :

383.12

Tentative Cost :

258.74

Saving

124.38

Exp. Upto Last Fy :

243.71

For CFY 2024-2025

Remaining :

139.41

Demand :

15.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

243.71

In Maintenance After Completion

Sanction on : 19 years 1 month ago

21 Oct 2005

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 4 months 3 weeks ago

30 Jun 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
6
6.000
0
0.000
0.000

Remark

view all

नाबार्ड के अन्तर्गत मैन्टनेन्स हेतु प्रस्ताव रू 17.84 लाख का गठित कर वृत्तीय कार्यालय, अल्मोड़ा को इस कार्यालय के पत्रांक 25672115सी. दिनांक 28.10.2024 द्वारा प्रेषित। -- as on 30-Oct-2024

Rating : 100

Forest Case Pending At : 13: AIP DFO

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: