Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.75 | 0.75 | 0.75 | 0 |
Closed Work 3W421 :
Administrative Approval Detail : 44/।।।(2)/18-49(एम0एल0ए0)/2017 दि0 08.01.2018
TS Amount (lakhs) : 23.07 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
26.07
Resanction Cost :
26.07
Tentative Cost :
26.07
Exp. Upto Last Fy : 21.63
For CFY 2024-2025
Remaining : 4.44
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 21.63
Work completed
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 100 %
Sanction on :
6 years 6 months ago
08 Jan 2018
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
2 years 3 months ago
31 Mar 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 16-Apr-2024