Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8.000 | 0 | 0.000 | 0.000 |
3W475 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 653/।।।(2)/19-24(प्रा0आ0)/2008 दि0 12.02.2019
TS Amount (lakhs) : 604.18 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
604.18
Resanction Cost :
604.18
Tentative Cost :
604.18
Exp. Upto Last Fy : 456.98
For CFY 2024-2025
Remaining : 147.20
Demand : 20.00
Allotment : 20.00
Exp in CFY : 20.00
Total Up to Date Exp : 476.98
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 5 months ago
12 Feb 2019
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
2 years 4 months ago
03 Mar 2022
Remark
Bottelneck: no issue
प्रतिकर भुगतान हेतु मुआवजा प्रस्ताव गठित। राजस्व विभाग द्वारा मुआवजा प्रस्ताव का सत्यापन किया जा रहा है। सत्यापन उपरान्त मुआवजा वितरण की कार्यवाही की जायेगी।
भौतिक रूप से कार्य मार्च 2022 में पूर्ण। रू0 20.00 लाख का सहायक अभियन्ता के नाम अग्रिम अग्रदाय खोला गया है। कार्य में बचत की धनराशि रू0 127.20 लाख मात्र समर्पित की जानी है।
-- as on 04-Jul-2024
Physical Peramenters