Work Profile Report [3W477]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 652/।।।(2)/19-47(प्रा0आ0)/2017 दि0 12.02.2019
TS Amount (lakhs) : 455.32 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
295.10
Resanction Cost :
295.10
Tentative Cost :
295.10
Exp. Upto Last Fy :
286.11
For CFY 2024-2025
Remaining :
8.99
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
286.11
Construction Started
Sanction on : 5 years 11 months ago
12 Feb 2019
Physical Progress:
At start of FY 2024-2025 :
77 %
Up to Date :
86 %
Tentative Completion date on : 1 year 9 months ago
31 Mar 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान एवं 4.00 किमी0 पार्ट-।। का कार्य पूर्ण। सेतु निर्माण व अन्य कार्य प्रगति पर है। -- as on 08-Nov-2021
Assets :