Work Profile Report [3W498]
Tenders
Project Activities
Samples
Administrative Approval Detail : 3381/।।।(2)/19-50(एम0एल0ए0)/2017 दिनांक 06.09.2019
TS Amount (lakhs) : 304.09 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
304.09
Resanction Cost :
304.09
Tentative Cost :
271.26
Saving
32.83
Exp. Upto Last Fy :
258.07
For CFY 2025-2026
Remaining :
46.02
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
258.07
Work completed
Sanction on : 5 years 9 months ago
06 Sep 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 2 months ago
31 Mar 2024
Actual Completion Date : 1 year 2 months ago
31 Mar 2024
Physical Linear Components
Remark
Overall Saving 32.83 has been recorded as expected cost of work reduced from 304.09 to 271.26 . -- as on 20-Jul-2024
Assets :