Work Profile Report [3W539]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 321/।।।(2)/21-49(एम0एल0ए0)/2017टीसी।। दि0 24.02.2021
TS Amount (lakhs) : 6351000 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
63.51
Resanction Cost :
63.51
Tentative Cost :
55.51
Saving
8.00
Exp. Upto Last Fy :
39.29
For CFY 2025-2026
Remaining :
24.22
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
39.29
Work completed
Sanction on : 4 years 2 months ago
24 Feb 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 9 months ago
30 Jun 2022
Actual Completion Date : 2 years 9 months ago
30 Jun 2022
Physical Linear Components
Remark
Overall Saving 8 has been recorded as expected cost of work reduced from 63.51 to 55.51 .
कार्य पूर्ण।
-- as on 11-Apr-2025
Assets :