Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.125 | 2.125 | 0.000 | 2.125 | 0.000 | 0.000 |
3W560 :
Administrative Approval Detail : 2329/।।।(2)/21-51(एम0एल0ए0)/2017टी0सी0 दिनांक 28.07.2021
TS Amount (lakhs) : 41.79 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.79
Resanction Cost :
41.79
Tentative Cost :
41.79
Exp. Upto Last Fy : 24.02
For CFY 2024-2025
Remaining : 17.77
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.80
Total Up to Date Exp : 24.82
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
28 Jul 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मार्ग में छोड़े गये पहाड कटान के डिफैक्ट कटिंग हेतु निविदा आमंत्रित। -- as on 08-Apr-2024
Physical Peramenters