Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.65 | 2.65 | 2.65 | 0 |
3W566 :
Administrative Approval Detail : 3584/III(2)/21-49(MLA)/2017 TC
TS Amount (lakhs) : 63.77 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
63.77
Resanction Cost :
63.77
Tentative Cost :
63.77
Exp. Upto Last Fy : 34.55
For CFY 2024-2025
Remaining : 29.22
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 34.55
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
10 Sep 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 year 5 months ago
01 Feb 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 05-Feb-2024
Physical Peramenters