Administrative Approval Detail : 387/XVII-B-1/2023-4/36)/2023 dated 14-03-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
9.30
Resanction Cost :
9.30
Tentative Cost :
9.30
Exp. Upto Last Fy :
8.69
For CFY 2024-2025
Remaining :
0.61
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
8.69
Work completed
Sanction on : 1 year 9 months ago
14 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 13-Mar-2024