Work Profile Report [3W653]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 895/07Yata-PMGSY-Ni III dated 16-05-2023
TS Amount (lakhs) : 420.25 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
420.25
Resanction Cost :
420.25
Tentative Cost :
420.25
Exp. Upto Last Fy :
415.83
For CFY 2025-2026
Remaining :
4.42
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
415.83
Work completed
Sanction on : 1 year 11 months ago
16 May 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 2 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 12-Apr-2025