Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.55 | 4.55 | 0.000 | 4.55 | 4.550 | 0.000 |
3W702 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 49618
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
276.09
Resanction Cost :
276.09
Tentative Cost :
276.09
Exp. Upto Last Fy : 79.41
For CFY 2024-2025
Remaining : 196.68
Demand : 135.00
Allotment : 48.00
Exp in CFY : 2.57
Total Up to Date Exp : 81.98
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 60 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
ठेकेदार द्वारा टाईमलाईन के अनुसार कार्य पूर्ण न किये जाने के कारण दि0 01.06.2024 को पुनः संयुक्त बैठक की गयी। जिसमें ठेकेदार द्वारा इण्टर कोट का कार्य 30.06.2024 तक, टापकोट का कार्य 15.08.2024 तक, डामरीकरण व अन्य समस्त अवशेष कार्य माह अक्टूबर 2024 तक पूर्ण किया जायेगा। -- as on 29-Jun-2024
Physical Peramenters