Work Profile Report [3W702]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E File No 49618
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
276.09
Resanction Cost :
276.09
Tentative Cost :
227.27
Saving
48.82
Exp. Upto Last Fy :
79.41
For CFY 2024-2025
Remaining :
196.68
Demand :
140.07
Allotment :
101.60
Exp in CFY :
101.60
Total Up to Date Exp :
181.02
Construction Started
Sanction on : 1 year 5 months ago
19 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
90 %
Tentative Completion date on : 5 days 11 hours from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य पूर्ण। अन्य कार्य प्रगति पर। -- as on 02-Dec-2024
Assets :
© PWD Uttarakhand