Work Profile Report [3W754]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E File No 64221/49
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
366.49
Resanction Cost :
366.49
Tentative Cost :
313.76
Saving
52.73
Exp. Upto Last Fy :
40.17
For CFY 2024-2025
Remaining :
326.32
Demand :
264.00
Allotment :
144.64
Exp in CFY :
90.87
Total Up to Date Exp :
131.04
Construction Started
Sanction on : 7 months 3 weeks ago
25 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
50 %
Tentative Completion date on : 6 months 6 days from now
25 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.00 किमी0 लम्बाई में टापकोट का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 03-Sep-2024