Work Profile Report : 3W93
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. 2454/111-2/05-07 (प्रा.आ.)/05 टी.सी.-। दि. 28.10.05
TS Amount (lakhs) : 160.22 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
160.22
Resanction Cost :
160.22
Tentative Cost :
137.33
Saving
22.89
Exp. Upto Last Fy :
112.55
For CFY 2025-2026
Remaining :
47.67
Demand :
24.78
Allotment :
0.80
Exp in CFY :
0.78
Total Up to Date Exp :
113.32
Work completed
Sanction on : 20 years 3 months ago
28 Oct 2005
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 years 2 months ago
24 Nov 2020
Actual Completion Date : 6 years 10 months ago
01 Apr 2019
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का भुगतान शेष। -- as on 03-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: