Work Profile Report [40W10]

मदमहेश्वर घाटी के अन्तर्गत तलसारी तोक से गौण्डार तक मोटर मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2847(1)।।।-2/05-79प्रा0आ0/05 दि0 19.12.05

TS Amount (lakhs) : 249.1 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

84.00

Resanction Cost :

249.10

Tentative Cost :

249.10

Exp. Upto Last Fy :

55.34

For CFY 2024-2025

Remaining :

193.76

Demand :

93.32

Allotment :

37.04

Exp in CFY :

36.10

Total Up to Date Exp :

91.44

Construction Started

Sanction on : 18 years 11 months ago

19 Dec 2005

Physical Progress:

At start of FY 2024-2025 :

6 %

Up to Date :

35 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
5
0.000
5
0.000
0.000

Remark

view all

किमी0 2 में पहाड़ कटान का कार्य प्रगति पर है। -- as on 27-Aug-2024

Rating : 38

Forest Case Pending At : 17: AIP Govt of India

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: