Work Profile Report [40W10]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2847(1)।।।-2/05-79प्रा0आ0/05 दि0 19.12.05
TS Amount (lakhs) : 249.1 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
84.00
Resanction Cost :
249.10
Tentative Cost :
249.10
Exp. Upto Last Fy :
55.34
For CFY 2024-2025
Remaining :
193.76
Demand :
93.32
Allotment :
37.04
Exp in CFY :
36.10
Total Up to Date Exp :
91.44
Construction Started
Sanction on : 18 years 11 months ago
19 Dec 2005
Physical Progress:
At start of FY 2024-2025 :
6 %
Up to Date :
35 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
किमी0 2 में पहाड़ कटान का कार्य प्रगति पर है। -- as on 27-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand