Work Profile Report [40W540]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : शा॰सं॰ 2451/।।।(2)/23-01 (प्रा॰आ॰)/2019लोक निर्माण अनुभाग-2॰ दिनंाक 21-07-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
260.86
Resanction Cost :
412.76
Tentative Cost :
412.76
Exp. Upto Last Fy :
183.11
For CFY 2024-2025
Remaining :
229.65
Demand :
229.65
Allotment :
206.09
Exp in CFY :
188.00
Total Up to Date Exp :
371.11
Construction Started
Sanction on : 1 year 3 weeks ago
21 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
70 %
Tentative Completion date on : 1 month 4 days ago
12 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
क्रैश बैरियर का कार्य पूर्ण। अवशेष कार्य प्रगति पर है। -- as on 01-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand