Work Profile Report [40W547]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : उत्तराखण्ड शासन लो॰नि॰वि॰, अनुभाग-2 का पत्रांक 4088ध् ।।।(2) ध्2023 (प्रा॰आ॰)ध्् 2023 दिनंाक 01-11-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
99.12
Resanction Cost :
99.12
Tentative Cost :
99.12
Exp. Upto Last Fy :
90.33
For CFY 2025-2026
Remaining :
8.79
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
90.33
Work completed
Sanction on : 1 year 5 months ago
01 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 months 1 week ago
17 Nov 2024
Actual Completion Date : 1 month 1 day ago
29 Mar 2025
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 15-Apr-2025
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: BHEERI BRIDGE Givadi gau bridge Kakdaghad bridge
© PWD Uttarakhand