Work Profile Report [43W585]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 2388/111(2)16-9(एमएलए)/ 2015 दि0 01.09.2016
TS Amount (lakhs) : 261.2 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
261.20
Resanction Cost :
261.20
Tentative Cost :
261.20
Exp. Upto Last Fy :
227.05
For CFY 2024-2025
Remaining :
34.15
Demand :
19.15
Allotment :
34.15
Exp in CFY :
7.25
Total Up to Date Exp :
234.30
Construction Started
Sanction on : 8 years 3 months ago
01 Sep 2016
Physical Progress:
At start of FY 2024-2025 :
74 %
Up to Date :
90 %
Tentative Completion date on : 3 months 1 day from now
27 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
किमी0 3 तक कार्य पूर्ण। किमी0 4 में कार्य प्रगति पर। -- as on 24-Oct-2024