Work Profile Report [43W748]

जनपद टिहरी के विधानसभा क्षेत्र घनसाली के अन्तर्गत स्यूरी से खवोगी मो0 मार्ग का नव निर्माण (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शा0 सं0 1194/111(2)/19-09(एम0एल0ए0)/ 2017 दि0 28.02.2019

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

6.44

Resanction Cost :

6.44

Tentative Cost :

6.44

Exp. Upto Last Fy :

0.30

For CFY 2025-2026

Remaining :

6.14

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.30

Alignment Approved

Sanction on : 6 years 1 month ago

28 Feb 2019

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

20 %

Tentative Completion date on : 5 days 22 hours ago

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
1
1
1
-

Remark

view all

प्रभागीय वनाधिकारी के पत्रांक सं0 2110/12-1 नई टिहरी द्वारा दिनांक 24.03.2025 को आपत्तियों में प्राप्त है । -- as on 04-Apr-2025

Rating : 20

Forest Case Pending At : 02: Division

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: