Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 0.000 | 4.5 | 4.500 | 2.000 |
44W620 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : GO no 501/III(2)/21-51/(ऍम० एल० ए०)/2017/टी० सी०-5 dated 07.01-2022
TS Amount (lakhs) : 346.89 Lacs
Financial Detail
Sanction Cost : 346.89 Lacs
Resanction Cost : 346.89 Lacs
Exp. Upto Last Fy : 233.39 Lacs
For CFY 2024-2025
Remaining : 113.50 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 13.94 Lacs
Total Up to Date Exp : 247.33 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
2 years 4 months ago
07 Jan 2022
Tentative Completion date:
3 weeks 6 days from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.50 कि0मी0 लम्बाई में पी0सी0 का कार्य पूर्ण। -- as on 29-May-2024
Physical Peramenters