Work Profile Report [45W287]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लोक निर्माण विभाग, उत्तराखण्ड, देहरादून के पत्रांक संख्या-895ध्07 याता0-पी0एम0जी0एस0वाई0-नि0-।।।, दि0 16.05.2023
TS Amount (lakhs) : 197.92 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
197.92
Resanction Cost :
197.92
Tentative Cost :
185.98
Saving
11.94
Exp. Upto Last Fy :
175.98
For CFY 2025-2026
Remaining :
21.94
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
175.98
Work completed
Sanction on : 1 year 9 months ago
16 Jun 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 7 months 1 week ago
30 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
work completed. -- as on 11-Apr-2025