Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
46W600 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या-37809 लोक निर्माण अनुभाग-2 देहरादून दिनांक 03 अगस्त 2023
TS Amount (lakhs) : 159.48 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
159.48
Resanction Cost :
159.48
Tentative Cost :
159.48
Exp. Upto Last Fy : 61.05
For CFY 2024-2025
Remaining : 98.43
Demand : 105.89
Allotment : 15.10
Exp in CFY : 0.00
Total Up to Date Exp : 61.05
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 80 %
Sanction on :
11 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
1 week 5 days from now
30 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 21-Dec-2023
Physical Peramenters