Administrative Approval Detail : श्शा0स0 1836/।।।(2)/18-10(एम.एल.ए.)/2016 दि0 13.07.2016
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
15.08
Resanction Cost :
15.08
Tentative Cost :
15.08
Exp. Upto Last Fy :
1.14
For CFY 2024-2025
Remaining :
13.94
Demand :
3.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.14
Construction Started
Sanction on : 8 years 2 months ago
13 Jul 2016
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
5 %
Tentative Completion date on : 6 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वनभूमि प्रस्ताव गठित किया जा रहा है। -- as on 26-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: