Work Profile Report [49W344]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : राष्टीय आपदा प्रबन्धन अभिकरण एन0एम0डी0ए0 भवन ए-सफदरजंग इन्कलेव नई दिल्ली के पत्र सं0-6-19/2011-मिट-।।/6918 दिनाॅक 17.07.2019
TS Amount (lakhs) : 600.66 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
600.66
Resanction Cost :
600.66
Tentative Cost :
600.66
Exp. Upto Last Fy :
553.64
For CFY 2025-2026
Remaining :
47.02
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
553.64
Work completed
Sanction on : 5 years 9 months ago
17 Jul 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 11 months ago
30 Apr 2021
Actual Completion Date : 3 years 11 months ago
30 Apr 2021
Physical Linear Components
Remark
कार्य पूर्ण, दायित्वों का भुगतान शेष। -- as on 30-Apr-2021
Assets :
© PWD Uttarakhand