Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 61.5 | 61.5 | 56.000 | 5.5 | 5.500 | 5.000 |
No of Bridges | 1 | 1 | 1 | 0 | 0 | 0 |
Span of Bridges [m] | 12 | 12 | 12.000 | 0 | 0.000 | 0.000 |
49W446 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1185/।।।(3)/2021-16(सी0आर0आई0एफ)/2021 दिनांक 27.10.2021
TS Amount (lakhs) : 5534.86 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5534.86
Resanction Cost :
5914.76
Tentative Cost :
5914.76
Exp. Upto Last Fy : 5,534.86
For CFY 2024-2025
Remaining : 379.90
Demand : 250.00
Allotment : 100.00
Exp in CFY : 0.00
Total Up to Date Exp : 5,534.86
Construction Started
Physical Progress:
At start of FY 2024-2025 : 97 %
Up to Date : 97 %
Sanction on :
2 years 8 months ago
27 Oct 2021
Tentative Completion date:
4 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मूल स्वीकृत कार्य पूर्ण किये जा चुके है एवं अतिरिक्त स्वीकृति जो कि शासनादेश संख्या 145/।।।(3)/2024-16 (सी0आर0आई0एफ0)2021 दिनांक 05.02.2024 को प्राप्त हुई, जिसका विचलन अधीक्षण अभियन्ता 8वां वृत्त लो0नि0वि0, नई टिहरी के पत्रांक 1201/147सी0-8/2021 दिनांक 18.03.2024 द्वारा अनुमोदित हुआ, के अन्तर्गत कार्य कराया जा रहा है, जिसमें डब्लू0बी0एम0 का कार्य लक्षित लम्बाई 28.00 कि0मी0 के सापेक्ष लगभग पूर्ण किया जा चुका है। कतिपय स्थानों पर स्लिप आने के कारण कार्य में विलम्ब हुआ है, जिसे साफ कराकर पुनः ठीक कराया जा रहा है। अतिरिक्त चैडाई मंे डी0बी0एम0 का कार्य 12.00 कि0मी0 में पूर्ण किया जा चुका है एवं बी0सी0 का कार्य 10.00 कि0मी0 में पूर्ण कराया जा चुका है। अवशेष कार्य मौसम अनुकूल होने पर किया जा सकेगा। -- as on 02-Jul-2024
Physical Peramenters