Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 5.000 |
49W515 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई पत्रावली संख्या- 32788, दिनांक 03.03.2023
TS Amount (lakhs) : 423.81 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
423.81
Resanction Cost :
423.81
Tentative Cost :
423.81
Exp. Upto Last Fy : 340.22
For CFY 2024-2025
Remaining : 83.59
Demand : 57.37
Allotment : 20.11
Exp in CFY : 18.83
Total Up to Date Exp : 359.05
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 90 %
Sanction on :
1 year 4 months ago
03 Mar 2023
Tentative Completion date:
6 months 1 week from now
31 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी1, जी2 व जी 3 तथा पी0सी0 का कार्य 5.00 किमी0 तक पूर्ण शेष कार्य प्रगति पर है। -- as on 28-Jun-2024
Physical Peramenters