Work Profile Report [49W608]
Tenders
Project Activities
alerts
Administrative Approval Detail : शासनादेश सं0 256/III(3)/2024-01(CRIF)2022 दिनांक 29.02.2024 & 322/III(3)/2024-14(CRIF)2024 दिनांक 16.03.2024 & 462/III(3)/2024-14(CRIF)2024 दिनांक 02.05.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2143.97
Resanction Cost :
2143.97
Tentative Cost :
2143.97
Exp. Upto Last Fy :
1,706.12
For CFY 2025-2026
Remaining :
437.85
Demand :
437.85
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1,706.12
Construction Started
Sanction on : 1 year 2 months ago
29 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
90 %
Tentative Completion date on : 3 weeks 4 days from now
10 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में रोड साइनेज का कार्य प्रगति पर है। -- as on 08-May-2025
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: रायपुर कुमाल्डा मो0 मार्ग के कि0मी0-15 है0मी0 8-10