Work Profile Report [4W157]

जनपद अल्मोड़ा में नैनी -जाना- गिनाई मोटर मार्ग का विस्तारीकरण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest
  • Remarks
  • Nabard
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : शासनादेश सं. 1499/111 (2)/05 -50 (प्रा.आ.)/05 दि. 5.8.05

TS Amount (lakhs) : 83.4 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

83.40

Resanction Cost :

83.40

Tentative Cost :

83.40

Exp. Upto Last Fy :

80.92

For CFY 2024-2025

Remaining :

2.48

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

80.92

Work completed

Sanction on : 19 years 4 months ago

05 Aug 2005

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 9 years 8 months ago

31 Mar 2015

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
6.000
0
0.000
0.000

Remark

view all

उक्त् मोटर मार्ग की विधिवत स्वीकृति शासनादेश सं. जी.आई. 1763/7-1-2008-600(2078)/2008 दिनांक 8.7.2008 द्वारा प्राप्त हो चुकी है। कार्य पूर्ण। पी.सी.सी. प्रेषित। परन्तु काश्तकारों द्वारा मुआवजे भुगतान से पूर्व आवश्यक दस्तावेज प्रस्तुत नहीं किये गये है। जिस कारण भुगतान की कार्यवाही नहीं हो पा रहा है। पी.सी.आर. मुख्य अभियन्ता, लो0नि0वि0, अल्मोड़ा के पत्रांक 2334/336याता.-कु./2020 दिनांक 30.5.20 द्वारा प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून को प्रेषित। -- as on 30-Apr-2024

Rating : 100

Forest Case Pending At : 21: Final

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: