Work Profile Report [4W32]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : शासनादेश सं. 869/111 (2)/ 09-45(एम.एल.ए.)./08टी.सी.दि0 2.3.09
TS Amount (lakhs) : 598.3 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
598.30
Resanction Cost :
598.30
Tentative Cost :
357.16
Saving
241.14
Exp. Upto Last Fy :
357.17
For CFY 2025-2026
Remaining :
241.13
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
357.17
Construction Started
Sanction on : 16 years 10 months ago
02 Mar 2009
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
70 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 241.14 has been recorded as expected cost of work reduced from 598.3 to 357.16 . एन0जी0टी0 के कारण कार्य बाधित। अनुपालन आख्या प्रभागीय वनाधिकारी, अल्मोड़ा के पत्रांक 2894/12-1(2) अल्मोड़ा दिनांक 25.10.2025 द्वारा वन संरक्षक उत्तरी कुमाऊं उत्तराखण्ड अल्मोड़ा प्रेषित। अनुपालन आख्या वन संरक्षक उत्तरी कुमाऊं उत्तराखण्ड अल्मोड़ा के पत्रांक 1129/12-1(2) दिनांक 30.10.2025 द्वारा प्रमुख वन संरक्षक/नोडल अघिकारी वन संरक्षण इन्दिरानगर फारेस्ट कालौनी उत्तराखण्ड देहरादून को प्रेषित -- as on 03-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand