Work Profile Report [4W33]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश सं. 853/ 111 (2)/ 09-06(मु.मं.घा)/08टी.सी.दि0 02.03.2009 & E file no 33425/I/103249/2023 दि0 01.03.2023
TS Amount (lakhs) : 557.91 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
210.00
Resanction Cost :
347.91
Tentative Cost :
226.98
Saving
120.93
Exp. Upto Last Fy :
206.98
For CFY 2024-2025
Remaining :
140.93
Demand :
20.00
Allotment :
20.00
Exp in CFY :
0.00
Total Up to Date Exp :
206.98
Work completed
Sanction on : 15 years 5 months ago
02 Mar 2009
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
24 Jun 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 120.93 has been recorded as expected cost of work reduced from 347.91 to 226.98 . -- as on 04-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: unknown bridge