Work Profile Report [4W545]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं. 275(ए)/111(2) /19-48(एम.एल.ए.)/2017 टी.सी.-1 दिनांक 22.1.2019
TS Amount (lakhs) : 330.85 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
330.85
Resanction Cost :
330.85
Tentative Cost :
320.32
Saving
10.53
Exp. Upto Last Fy :
310.32
For CFY 2025-2026
Remaining :
20.53
Demand :
10.00
Allotment :
10.00
Exp in CFY :
0.00
Total Up to Date Exp :
310.32
Work deferred
Sanction on : 6 years 11 months ago
22 Jan 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 weeks ago
15 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 10.53 has been recorded as expected cost of work reduced from 330.85 to 320.32 . पी.एम.जी.एस.वाई.-4 में स्वीकृत होने के कारण कार्य में बचत है। निरस्तीकरण प्रस्ताव गठन की कार्यवाही गतिमान है। -- as on 02-Jan-2026
Assets :