Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.2 | 5.7 | 5.700 | 0 | 0.000 | 0.000 |
4W593 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं. 194(1)/111(2)/20-48(एम.एल.ए.)/2017 टी.सी. दिनांक 10.2.2021
TS Amount (lakhs) : 401.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
401.41
Resanction Cost :
401.41
Tentative Cost :
401.41
Exp. Upto Last Fy : 374.56
For CFY 2024-2025
Remaining : 26.85
Demand : 20.00
Allotment : 10.00
Exp in CFY : 8.37
Total Up to Date Exp : 382.93
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 100 %
Sanction on :
3 years 5 months ago
10 Feb 2021
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। अगस्त,2024 तक पी0सी0आर0 प्रेषित कर दी जायेगी। वर्तमान में कार्य डी0एल0पी0 अवधि में है 3 प्रतिशत अनुरक्षण हेतु रू. 1014000.00 मात्र बजट स्वीकृत है। -- as on 04-Jul-2024
Physical Peramenters