Administrative Approval Detail : ई फाईल नं0 49297
TS Amount (lakhs) : 26.68 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
61.97
Resanction Cost :
26.68
Tentative Cost :
26.52
Saving
0.16
Exp. Upto Last Fy :
18.77
For CFY 2025-2026
Remaining :
7.91
Demand :
6.75
Allotment :
9.25
Exp in CFY :
0.00
Total Up to Date Exp :
18.77
Construction Started
Sanction on : 2 years 10 months ago
20 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 2 months 1 week from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 0.16 has been recorded as expected cost of work reduced from 26.68 to 26.52 . डी0पी0आर0 गठन की कार्यवाही गतिमान है। -- as on 03-Jan-2026