Work Profile Report [4W97]

जालली-तकुल्टी-भन्टी- पटास मोटर मार्ग ।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest
  • Remarks
  • Nabard
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनदेश सं.299/लो.नि.-2-04-16(प्रा.आ.) / 04 दिनांक 28.2.04

TS Amount (lakhs) : 118.79 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

139.00

Resanction Cost :

139.00

Tentative Cost :

139.00

Exp. Upto Last Fy :

108.44

For CFY 2024-2025

Remaining :

30.56

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

108.44

Work completed

Sanction on : 20 years 9 months ago

28 Feb 2004

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 2 years 8 months ago

31 Mar 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
5
4.500
0.5
0.000
0.000

Remark

view all

4.50 किमी. में पहाड़ कटान एवं 4.50 किमी. में पार्ट-2 का कार्य पूर्ण।पी.सी.आर. मुख्य अभियन्ता, लो0नि0वि0, अल्मोड़ा के पत्रांक 2334/336याता.-कु./2020 दिनांक 30.5.20 द्वारा प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून को प्रेषित। भारत सरकार, पर्यावरण एवं वन मंत्रालय के पत्र संख्या 8बी./यू.सी.पी./06/20/2010/एफ.सी./626 दिनांक 26.8.2010 द्वारा विधिवत स्वीकृति प्राप्त। -- as on 14-May-2024

Rating : 100

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1 Road 2

Bridges on The Basis of AI:

© PWD Uttarakhand