Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.1 | 4.1 | 4.1 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 |
51W7 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 548/111-2/09-71 (र्पा0आ0)/08 दिनांक 2.3.09
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 191.22 Lacs
Resanction Cost : 191.22 Lacs
Exp. Upto Last Fy : 17.20 Lacs
For CFY 2024-2025
Remaining : 174.02 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 17.20 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
15 years 2 months ago
02 Mar 2009
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
इस कार्यालय के पत्र सं 1728/1C Dt. 21-05-2022 एवं 2774/2C Dt. 30.07.2022, 4977/2C Dt. 26.12.22 के द्वारा जिलाधिकारी महोदय देहरादून को क्षतिपूरक वृक्षारोपण हेतु 3.3075 है0 भूमि के सापेक्ष दोगुनी 6.6150 हे0 भूमि हेतु पत्र लिखा गया है। क्षतिपूरक वृक्षारोपण मानचित्र प्रभागीय वनाधिकारी चकराता वन प्रभाग चकराता से हस्ताक्षर उपरान्त इस कार्यालय को प्राप्त। प्रकरण पर अग्रिम कार्यवाही की जा रही है। -- as on 05-May-2024
Physical Peramenters