Work Profile Report [52W457]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 ई पत्रावली संख्या-37518 अनुभाग-2, देहरादून दिनांक 22 मार्च 2023
TS Amount (lakhs) : 181.79 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
181.79
Resanction Cost :
195.03
Tentative Cost :
195.03
Exp. Upto Last Fy :
152.74
For CFY 2024-2025
Remaining :
42.29
Demand :
13.00
Allotment :
40.00
Exp in CFY :
15.74
Total Up to Date Exp :
168.49
In Maintenance After Completion
Sanction on : 1 year 8 months ago
22 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 weeks ago
31 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण ,दायित्वों का भुगतान शेष -- as on 19-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: