Work Profile Report [53W1553]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 5687/।।।(2)/21-19(एम.एल.ए.)2017 दिनांक 23.11.2021
TS Amount (lakhs) : 131.58 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
131.58
Resanction Cost :
131.58
Tentative Cost :
131.58
Exp. Upto Last Fy :
129.11
For CFY 2024-2025
Remaining :
2.47
Demand :
2.40
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
129.11
Work completed
Sanction on : 3 years 1 month ago
23 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date : 1 year 7 months ago
30 Apr 2023
Physical Linear Components
Remark
एस0डी0बी0सी0 का कार्य माह 12/2022 में पूर्ण। इण्टर लाॅकिग टाईल्स का कार्य माह 04/2023 में पूर्ण। -- as on 11-May-2023
Assets :