Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.973 | 4.973 | 4.973 | 0 |
Closed Work 54W1069 :
Administrative Approval Detail : शासनादेश संख्या 2394/।।।(2)/21-17 (एम0एल0ए0)2017 टी0सी0-।।, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 04.08.2021
TS Amount (lakhs) : 298.79 Lacs
Financial Detail
Sanction Cost : 298.79 Lacs
Resanction Cost : 298.79 Lacs
Exp. Upto Last Fy : 291.02 Lacs
For CFY 2024-2025
Remaining : 7.77 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 291.02 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
04 Aug 2021
Tentative Completion date:
1 year 7 months ago
10 Nov 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 13-Dec-2022
Physical Peramenters