Work Profile Report [54W927]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0- 1265/।।।(2)/19-17 (एम0एल0ए0)/2017, लोक निर्माण अनुभाग-2, देहरादून, दिनांक 07.03.2019
TS Amount (lakhs) : 85.61 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
85.61
Resanction Cost :
85.61
Tentative Cost :
85.61
Exp. Upto Last Fy :
81.05
For CFY 2024-2025
Remaining :
4.56
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
81.05
Work completed
Sanction on : 5 years 9 months ago
07 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
70 %
Up to Date :
100 %
Tentative Completion date on : 3 years 4 months ago
25 Aug 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 18-Apr-2023
Assets :