Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
56W687 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के ई-पत्रावली संख्या -35334 दिनांक 07.08.2023
TS Amount (lakhs) : 61.04 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
61.04
Resanction Cost :
61.04
Tentative Cost :
61.04
Exp. Upto Last Fy : 55.92
For CFY 2024-2025
Remaining : 5.12
Demand : 2.12
Allotment : 0.00
Exp in CFY : 2.33
Total Up to Date Exp : 58.26
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
07 Aug 2023
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
माह मार्च 2024 में स्टेज-। (पहाड कटान) का कार्य पूर्ण दायित्व का भुगतान शेष। -- as on 06-Apr-2024