Work Profile Report [59W1828]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 49/।।।(3)/2021-27(सी.आर.एफ.)2019 दि0 11.01.2021
TS Amount (lakhs) : 2357.46 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2602.24
Resanction Cost :
2602.24
Tentative Cost :
2602.24
Exp. Upto Last Fy :
2,292.67
For CFY 2024-2025
Remaining :
309.57
Demand :
64.79
Allotment :
64.79
Exp in CFY :
64.50
Total Up to Date Exp :
2,357.17
Work completed
Sanction on : 3 years 10 months ago
11 Jan 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 9 months ago
31 Jan 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work completed 03/2024 -- as on 02-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: