Work Profile Report [5W24]

जनपद बागेश्वर में कठपूड़िया-सेराघाट मोटर मार्ग का विस्तार।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 196 /लो0नि0-2 /04-10 (प्रा0आ0)/ 2004 दिनांक 17-2-2004

TS Amount (lakhs) : 183.03 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

193.68

Resanction Cost :

193.68

Tentative Cost :

193.68

Exp. Upto Last Fy :

177.46

For CFY 2024-2025

Remaining :

16.22

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

177.46

Unstarted Work

Sanction on : 20 years 9 months ago

12 Feb 2004

Physical Progress:

At start of FY 2024-2025 :

75 %

Up to Date :

75 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
12
12
12.000
0
0.000
0.000
Bridge
1
0
0 (0.000m)
0
0 (0.000m)
0 (0.000m)

Remark

view all

उक्त स्वीकृति के अन्तर्गत 12 अनुबन्ध गठित किये गये थे। जिसमें 11 अनुबन्धों का अन्तिमीकरण कर दिया गया है। शेष 1 अनुबन्ध का अन्तिमीकरण की कार्यवाही गतिमान है। -- as on 24-Dec-2022

Rating : 92

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: