Work Profile Report [5W7]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2490/111- 2/08-61 (प्रा0आ0)/ 2007 दि0 25.07.2008
TS Amount (lakhs) : 282.65 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
517.50
Resanction Cost :
517.50
Tentative Cost :
517.50
Exp. Upto Last Fy :
420.06
For CFY 2024-2025
Remaining :
97.44
Demand :
77.00
Allotment :
65.00
Exp in CFY :
52.93
Total Up to Date Exp :
472.99
Work completed
Sanction on : 16 years 3 months ago
25 Jul 2008
Physical Progress:
At start of FY 2024-2025 :
76 %
Up to Date :
100 %
Tentative Completion date on : 6 months 3 weeks ago
01 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सेतु का कार्य पूर्ण। -- as on 25-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: