Work Profile Report [5W804]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 374(1)/छत्ताीस(2)/2021-25-भूमि/09/20, दिनांक 07.07.2021
TS Amount (lakhs) : 56.02 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
56.02
Resanction Cost :
56.02
Tentative Cost :
56.02
Exp. Upto Last Fy :
34.26
For CFY 2024-2025
Remaining :
21.76
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
34.26
Work completed
Sanction on : 3 years 5 months ago
07 Jul 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date : 2 years 1 month ago
31 Oct 2022
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 29-Aug-2023
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: 36.00 m span steel bridge 6m Span RCC motor bridge 7.20m span RCC motor bridge
© PWD Uttarakhand