Administrative Approval Detail : 1099/।।।(3)/2021-36(सी0आर0आई0एफ0)/2021 दिनांक 04.10.2021
TS Amount (lakhs) : 104.65 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
104.65
Resanction Cost :
104.65
Tentative Cost :
104.65
Exp. Upto Last Fy :
101.69
For CFY 2024-2025
Remaining :
2.96
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
101.69
Work completed
Sanction on : 3 years 1 month ago
04 Oct 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date : 2 years 8 months ago
01 Mar 2022
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 01-Sep-2022
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3 Road 4 Road 5
Bridges on The Basis of AI: 48 Papey Motor Bridge 72m Span motor Bridge near District Hospital 65 m span suspension bridge at thaklar 12m Span RCC bridge (Dyangar Section) 60m Span Steel girder bridge (Runikhet-Gandigram motor road) 48m span Motor Bridge at Simar Kansyari MR 63 m span suspension bridge near house of Dungar Singh Parihar